Rogue River Rd (Plainfield Bridge 16)

Back

The project consists of removing select beams from the Plainfield No. 16 Bridge and replacing these beams.  The project also includes HMA removal, construction of a new bridge railing, approach work with HMA paving.  The project will be constructed under a complete closure of Rogue River Drive with a detour posted. 

 

Important dates:

Friday August 30 – Scheduled Open To Traffic – The south quadrants will have temporary barriers in place to allow future gas work.

 

Projected for September 10 or 15 – DTE arrives back and bridge will be one lane of traffic and controlled with a temporary traffic signal.  DTE will have 1 to 2 weeks of gas main work.

 

Projected for September 25 to 30 – Our bridge contractor will come back and finish the guardrail.  DTE will then pull the temporary traffic signals and the project will be completely open.