Peach Ridge Ave and Rusco St

Back

This project includes widening of Peach Ridge Avenue to provide center turn lanes for MDOT signal installation. The project will consist of tree removal, asphalt and concrete removal, earthwork, aggregate base, culvert extensions, storm sewer, concrete curb and gutter, HMA paving, restoration and pavement markings.

 

Cul-de-sac construction on Rusco Road, east of Peach Ridge Avenue, will also take place under the same closure.

 

M-37 remains open throughout project.

 

Schedule (subject to change):

  • Start: August 19, 2024
  • Open to Traffic: September 7, 2024
  • Project Complete: September 14, 2024