Drain Commission Project: Reconstruct to 2-lane all-season. Work includes tree removal, earthwork, 24”-30” storm drain, HMA pavement, pavement markings and restoration. Through traffic will be detoured. Tree removal by March 31, 2025. Roadwork shall be phased over 2 construction seasons and set to begin in late Spring 2026.