The project will involve cold milling of the existing Hot Mix Asphalt (HMA) between the existing curbs, followed by the placement of two new courses of HMA. Prior to milling and paving operations, all sidewalk ramps within the project limits will be removed and replaced to comply with current accessibility standards.
Throughout the duration of the project, northbound traffic will remain open, and access to all businesses and residences within the project limits will be maintained. Southbound traffic will be detoured via O’Connor Street.