Byron Township

Back

The Kent County Road Commission (KCRC) in collaboration with Byron Township is contracting with Rieth-Riley

to complete a full-width repaving of select local streets. The project is to be completed within 2025 contract limits, projected to begin late June, weather permitting.

 

The resurfacing project will consist of repaving with hot mix asphalt the entire road surface of the identified streets.

 

Neighborhood Paving Guidance for Property Owners

 

List of Streets Receiving Improvement

PROJECTED START: June 9 (subject to change)

-82nd Street: Freeland Ave to Byron Center Ave 

-Freeland Avenue: 84th Street to 82nd Street 

-Harlow Avenue: Sherwood Street to End 

-Merton Avenue: 84th Street to End 

-Sherwood Street: Byron Center Ave. to End 

-Byron Creek Drive: 84th St to Creekside Drive 

-Cool Ridge Dr: Morning Dew Dr. to Creekside Dr. 

-Creekside Drive: Byron Creek Drive to Amber Creek Drive 

-Misty Ridge Blvd: Morning Dew Dr. to Burlingame Ave 

-Morning Dew Dr: Byron Creek to Burlingame Ave 

-Alro Drive: Morning Dew Drive to End 

-Broda Drive: Morning Dew Dr. to End 

-Land Ridge Drive: Cool Ridge Dr. to Morning Dew Dr. 

-Landstar Drive: Misty Ridge Dr. to Morning Dew Dr. 

-Morning Dew Court: Morning Dew Dr. to End 

 

Projected Start: July 7, 2025 (subject to change)

Homerich Avenue: 76th Street to 84th Street