Cannon Township

Back

The Kent County Road Commission (KCRC) in collaboration with Cannon Township is contracting with Michigan Paving and Materials to complete a full-width repaving of select local streets. The project is to be completed within 2025 contract limits, projected to start early June, weather permitting.

 

About the Project: The resurfacing project will consist of repaving with hot mix asphalt the entire road surface of the identified streets.

 

For more information, click the link below:

Neighborhood Paving Guidance for Property Owners

 

List of Streets PROJECTED START 10/15 (Schedule subject to change)

Eldred Drive: Yound Avenue to East

Eldred Avenue: Southerly to Backaround

Eldred Avenue: Northerly to Cul-de-sac

 

PAVING COMPLETE - RESTORATION IN PROGRESS

 

List of Streets COMPLETED (6/6)

-Davies Drive: Ramsdell Drive to End

-Goldenrod Drive: Davies Drive to Ramsdell Drive

-Northport Drive: 9 Mile Road to End

 

List of Streets COMPLETED (8/7)

Blakely Drive: Cannonsburg Road to 7 Mile Road

 

Restoration: Upon completion of the project, grass in the right-of-way will be restored by KCRC within approximately two-to-four weeks. Topsoil and grass seed will be placed in disturbed areas. It is the homeowner’s responsibility to water and maintain the area to assist with regrowth.