Phase I – Kent County Road Commission (KCRC)
- Phase I work will be completed by KCRC and includes:
- - Encasement of the existing steel abutments with reinforced concrete
- - Removal of the existing hot-mix asphalt (HMA) from the bridge deck
- - Patching of the concrete bridge deck
- - Removal and replacement of guardrail at the project location
The estimated duration: 35 days
Phase II – Miller Bridge
- Phase II work will be completed by Miller Bridge and includes:
- - Cleaning and coating (painting) of the steel beams and abutment faces
- - Installation of shear stud devices on the beams to eliminate the current load restrictions on the bridge
The estimated duration for Phase II is 35 days.