Open cut excavation of 18-inch and 21-inch sanitary sewer completed in three phases:
Phase 3A: under 64th St from approx.1,100ft east of Ivanrest Ave, continuing east to Kent Trails crossing.
Phase 3B: From Kent Trails crossing on 64th St, continuing east cross-country to Byron Center Ave.
Phase 3C: Bore and jack under Byron Center Ave, south of 68th St, continue south along the east side of Byron Center Ave for approx. 1,300ft. Work to include full-width street restoration and widening on 64th St.
Closed to through traffic; access maintained for properties within work zone.