The Kent County Road Commission (KCRC) in collaboration with Cascade Township is contracting with Michigan Paving and Materials to complete a full-width repaving of select local streets, listed below. The project is to be completed within 2026 contract limits, between May and October, 2026, weather permitting.
- Click Here for Neighborhood Improvement Information
|
Aquafria Court: Goodwood to End |
| Burger Drive: Goodwood Dr. to Woodbrook Dr. |
| Burger Drive: Thornapple River to Goodood Dr |
| Forest Valley Court: Forest Valley Dr. to End |
| Forest Valley Drive: Oak Tree Dr. to Oakmont Dr. |
| Goodwood Court: Goodwood to End |
| Goodwood Drive: Burger Dr. to Maplecrest Dr |
| Maplecrest Court: Maplecrest to End |
| Maplecrest Drive: Goodwood Dr to End |
| Oak Creek Court: Forest Valley Dr. to End |
| Oak Tree Drive: Maplecrest Dr. to Woodbrook Dr. |
| Oakbluff Drive: Woodbrook Drive to End |
| Oakcrest Court: Maplecrest to End |
| Oakmont Drive: Forest Valley Dr. to Ridgemont |
| Placita Court: Goodwood Dr. to End |
| Ridgemont Drive: Woodbrook to Thornapple River |
| White Oak Court: Forest Valley Dr. to End |
| Thornapple River Dr: Thornhills Ave. to Cascade Rd. |
| Jacksmith Ave: 28th St. to Thornbrook Ave |
| Thornbrook Dr: Thornhills Ave. to Jacksmith Ave. |
| Hall Street: Paradise Lake Dr. to Oak Hollow Ave. |
| Marsman Avenue: Hall Street to End |
| Oliver Woods Court: Oliver Wood Dr. to End |
| Oliver Woods Drive: Thornapple River Dr. to End |